Damage to Cortina’s Sliding Centre? Simico clarifies: “Further work needed for a track that is already among the best in the world”

Foto di Redazione
Photo information

Pentaphoto

Milano Cortina 2026facilities

Damage to Cortina’s Sliding Centre? Simico clarifies: “Further work needed for a track that is already among the best in the world”

The company managing Cortina’s sliding track, built in record time for a major edition of the Olympic Games (the facility received unanimous praise), explains that only some work is needed to restore full operation, ahead of the major events already awarded by the FIL, given that Cortina will host a stop of the 2026/27 Luge World Cup (and again at the end of 2028 and in 2029).

In recent days, some media outlets have reported on damage sustained by Cortina’s Sliding Centre, one of the most important venues, which hosted all the luge events (with tremendous success for the Italian athletes), as well as skeleton and bobsleigh, at the latest Olympic Games. The venue will be crucial for the entire sliding sports movement in Italy due to its use over the coming years.

Simico wanted to clarify that while renovation work is indeed necessary at the facility, there is no cause for alarm in this regard, even though the Italian championships have been cancelled.

Indeed, the FIL, the International Luge Federation, has already awarded Cortina World Cup stops during the next Olympic cycle, with the “Eugenio Monti” track set to take centre stage in the 2026/27 season (during the week from 8 to 14 February), and then again in December 2028 and one year later, in what will be the winter of the Games in France.

“With regard to the press reports circulated in recent days about the future of Cortina’s Sliding Centre, Società Infrastrutture Milano Cortina 2026 specifies that the claim that the new facility is ‘out of operation’ is unfounded – Simico stated in its release – The track, built in record time – 305 days – received praise and recognition at international level during the Games, with more than 22,000 runs.

As set out in the schedule, the final construction activities will be completed in the coming weeks. It should also be stressed that the figures reported in the press concerning possible ‘multi-million-euro damage’ to the facility do not reflect the facts and, in any event, have not been certified by any technical document issued by this Company. Once the dismantling phase connected with the Olympic Games has been completed, the Company will regain full control of the facility and continue with the work under its responsibility, with the aim of offering athletes one of the best tracks in the world, also in view of the competitions already scheduled, starting with those organised by the FIL through to 2030.”