Argentera Municipality working to reopen chairlift

Partenza seggiovia e piste
Photo information

Anonymous

PiedmontCableway Finance

Argentera Municipality working to reopen chairlift

The Municipality of Argentera is carrying out extraordinary maintenance work to restore the two-seater Pian del Beu chairlift, which has been closed since 2019. The aim is to test the lift by December and identify an operator to be temporarily entrusted with its management for the winter season.

This winter, skiing could return to Argentera. The conditional is necessary, given the numerous technical and bureaucratic details that still need to be completed. However, the Municipality, which owns the facilities, aims to return the ski area to skiers as early as this season, testing the chairlift by December. The Alta Valle Stura resort also includes 3 surface lifts and extends from 1,630 to 2,480 metres, with the slopes predominantly facing north-east. Thanks to its wild landscapes and powder snow, Argentera is particularly well known among off-piste skiing enthusiasts and is also an ideal destination for families and beginners, thanks to its intimate and peaceful atmosphere. 

The work carried out on the chairlift in recent months involves a major extraordinary maintenance project: in addition to structural inspections and the overhaul of all moving components, the lift's upper station has been completely rebuilt. 

The construction site has been affected by a series of technical and bureaucratic issues that have slowed its completion and extended the timeline. 

As Argentera Mayor Monica Ciaburro explained to targatocn.it, one of the issues affecting the schedule concerns the electricity supply to the drive station. After the procedures to transfer ownership of the meter to the Municipality—previously registered to the company Valle Bianca—had been resolved, an underground fault caused by the melting of a medium-voltage cable was discovered. A specialist company, equipped with specific instruments, had to be brought in to locate the break, at a cost of approximately 6,000 euros. 

The electrical line and installation of the chairlift's new drive station have now been completed. Some details at the service station still need to be finished. Another important project concerned the safety of the line and the retaining wall. As part of the inspections, a forestry technician was commissioned to survey the trees located near the chairlift line. The assessment revealed widespread instability, making it necessary to cut down a considerable number of trees along the line. At the same time, forestry workers from the Piedmont Region also intervened to catch up on overdue maintenance along the slopes, carrying out pruning and cutting back protruding branches.

As for the retaining wall, the Landscape Commission has issued a favourable opinion on the design variations. The documentation has been forwarded to the Superintendency, which will have 60 days to give its opinion.

To allow the work to be completed and deal with any further problems, the Municipality will grant another technical extension to the deadline for completion, tentatively between the end of November and the first days of December. 

However, the Municipality's financial situation is also weighing on progress. “The contractor has issued the invoice certifying that 51% of the work has been completed, the threshold required to request the second tranche of regional funding. The Piedmont Region has already prepared the payment order, but the funds have not yet actually been transferred by the Regional Treasury Department,” Mayor Ciaburro told targatocn.it.

This is a particularly significant difficulty for the Municipality of Argentera, which is still in the final stage of its financial insolvency procedure and therefore cannot resort to a bank advance to cover payments while awaiting the transfers. 

The dispute with the company holding the facility's management contract also remains unresolved. The Municipality has already appointed a lawyer and initiated proceedings through a payment order to obtain the return of the premises and the clearing of the facilities, but the situation has not yet been resolved.

This issue is intertwined with the prospects for the winter season. The Administration is considering the possibility of arranging temporary management, should an operator willing to take over the facility once the construction work is completed be identified.

© ALL RIGHTS RESERVED
297
Social media engagement

Latest in Regioni

Latemar Dolomites, season starts on November 27 with the new “Obereggen” chairlift

Latemar Dolomites, season starts on November 27 with the new “Obereggen” chairlift

After the abundant snowfall across the entire Alpine arc in recent days, the winter season will begin on Friday, November 27, in Obereggen, a resort 20 minutes from Bolzano. The gates will open as early as 8:30 a.m., with four lifts. From 7:00 p.m., it will also be possible to ski at night. Starting Saturday, November 28, a total of eleven lifts in the Latemar Dolomites ski area will be open, including the link between Obereggen and Pampeago. The lifts in Predazzo will open on Friday, December 4.