San Giacomo di Roburent, Piedmont Region and Province of Cuneo invest to keep the Monte Alpet chairlift in operation

San Giacomo di Roburent, Regione Piemonte e Provincia di Cuneo investono per mantenere in funzione la seggiovia del Monte Alpet
Photo information

YouTube

Piedmont2026/2027 winter season

San Giacomo di Roburent, Piedmont Region and Province of Cuneo invest to keep the Monte Alpet chairlift in operation

Investment of over €1.1 million for the general overhaul to extend the technical life of the two-seater Pamparato-Monte Alpet chairlift. Work will begin in September, at the end of the summer season, with the aim of completing it by December 8. The chairlift operates year-round and provides access to the beautiful panoramic summit of Monte Alpet. In addition to transporting pedestrians, in winter it is one of the main lifts in the ski area, while in summer it serves a popular bike park.

A busy period of work is getting under way for the San Giacomo di Roburent ski resort. In addition to the work involving the reactivation of the Bric Colmé chairlift, following the serious damage caused by the arson attack in August 2024 and funded by the Piedmont Region and the Municipality of Roburent, the Monte Alpet chairlift will also be the subject of a major extraordinary maintenance investment. This is the main lift at San Giacomo di Roburent: in winter, it provides access to and use of the ski slopes in the Monte Alpet area, while also allowing pedestrians to reach the mountain hut and the panoramic area at altitude. In summer, downhill trails are added to its pedestrian transport service. The general overhaul will extend its technical life by a further 10 years, ensuring the continued operation of the entire San Giacomo tourist and sports resort. 

The total cost of the project amounts to € 1,110,500, including VAT. The project has been approved for funding under the Piedmont Region Snow System Investments Call 2025-2030. The regional contribution amounts to € 999,450, equal to 90% of the eligible cost. The Province of Cuneo, which owns the lift, has provided € 111,050 from its own funds to co-finance the remaining share. 

With work starting on September 1, the regular running of the summer season will not be affected. 
The chairlift and Bike Park are currently already open every weekend and will continue to operate in the same way in June and July. In August, the chairlift will be open every day from August 8 to 23, as well as during the final weekend of the month.

© ALL RIGHTS RESERVED
2
Social media engagement

Latest in Regioni

Latemar Dolomites, season starts on November 27 with the new “Obereggen” chairlift

Latemar Dolomites, season starts on November 27 with the new “Obereggen” chairlift

After the abundant snowfall across the entire Alpine arc in recent days, the winter season will begin on Friday, November 27, in Obereggen, a resort 20 minutes from Bolzano. The gates will open as early as 8:30 a.m., with four lifts. From 7:00 p.m., it will also be possible to ski at night. Starting Saturday, November 28, a total of eleven lifts in the Latemar Dolomites ski area will be open, including the link between Obereggen and Pampeago. The lifts in Predazzo will open on Friday, December 4.